We are incredibly fortunate to be able to work on such a beautiful and historic project.
Phase one of the works has been to supply an independent splay scaffold to either side of the screen walls. The walls have been carefully dismantled, each piece of stone measured and numbered so it can be re cut out of new stone by Boden & Ward Master Stonemasons.
The scaffold has subsequently been dismantled to allow piling to take place and new footings to be poured.
Phase two is to erect a two lift load bearing independent play scaffold once again to either side of the screen walls for the timely rebuilding process. This time with the addition of a load bearing 3rd lift of scaffold to suspend heavy duty lifting tackle. We will also erect eight 10KNm2 loading platforms.
We will keep this gallery updated as the project progresses.